Haihao Group congratulates COOEC on the new milestone of FPSO P79 project

Haihao Group congratulates COOEC on the new milestone of FPSO P79 project

On January 26, 2022, COOEC successfully completed the first topside module of the 400,000-ton floating production, storage and offloading (FPSO) P79 project of Petrobras and officially delivered it and set sail, once again providing a new opportunity for COOEC. Earn new glory.

The P79 project is the eighth FPSO of Petrobras in the Buzios oil field. It has a total length of 345.3 meters, a molded width of 60 meters, a molded depth of 34.3 meters, and a weight of about 130,000 tons. It is one of the largest FPSOs currently under construction in the world. one. After the FPSO is put into operation, the production capacity will be 180,000 barrels of oil and 7.2 million cubic meters of natural gas per day, the oil storage capacity will be 2 million barrels of crude oil, and the operating water depth will exceed 2,000 meters. It will be connected to 8 production wells and 6 water injection wells.

COOEC completed FPSO P97 project

COOEC completed FPSO P97 project

The project undertaken by COOEC includes the construction of 13 modules of about 30,000 tons of topside modules, as well as shipment, partial detailed design, processing design, material procurement and other work. As the core compressor module package of the entire ship, the project involves 153 large-scale compressor modules. For mechanical equipment installation work, more than 50% of equipment requires side plugs.

Faced with severe challenges such as high construction technology requirements, difficult safety and quality management, and a large number of side-mounted equipment, the project team implemented a monthly rolling plan, a special module plan, and a full-process application engineering project construction management system to implement the integration of process modules and pipe gallery modules. construction, greatly improving the level of project integration, completing the side-loading operation of large equipment exceeding 200 tons, reaching the leading level of side-loading equipment in the industry.

The construction of the topside module of the P79 project is the second large-scale deepwater FPSO project in Brazil in South America that COOEC participated in after delivering two 350,000-ton FPSO P67/P70 projects for Petrobras.

Over the years, COOEC has actively responded to the national “Belt and Road” initiative, actively promoted China’s “high-end manufacturing” to go global, and has successively completed the construction of 45 “Belt and Road” project units such as the world’s first polar LNG plant and the Yamal project. Established friendly cooperative relations with dozens of international energy companies and engineering companies around the world, becoming Saudi Aramco’s first qualified offshore platform construction site in China, and the first domestic enterprise to obtain Shell HSSE (Health, Safety, Security, Environmental Protection) green certification , continue to consolidate the “Made in China” international brand. As a strategic reserve supplier of Offshore Oil Engineering, Haihao Group has cooperated with Offshore Oil Engineering in the construction of multiple FPSO pipeline system projects. We are very happy to see Offshore Oil Engineering making new achievements and look forward to more cooperation with Offshore Oil Engineering in the future. Many cooperation opportunities.